Expanding a food factory while production continues

Expanding a food factory while production continues takes more than making room for an extra line. Storage, dispatch, energy supply and hygiene must also be able to accommodate growth. The expansion of Puratos in Erembodegem shows why these factors need to be considered together from the outset. Uticon, now part of Haskoning, developed a phased approach that linked logistics and process design.
The 2018-2019 expansion began with the flow of goods. Additional storage space and a warehouse with 9,000 pallet locations were added. The number of loading bays rose from two to six. Two packaging lines and a production line followed. This sequence highlights an important requirement: additional production capacity must also be handled further downstream in the factory.
Coordinating construction phasing and logistics
Throughout the works, employees, contractors and goods still needed to reach their destinations. Barriers, tents and screens separated the construction site from production. Traffic lights helped manage peak periods, while information screens kept employees informed.
This makes the interim phase a design challenge in its own right. Which passageways need to remain open? Where can deliveries be received? How can a contractor reach their work area? The answers help determine whether construction and production can practically continue side by side.

Process design determines what is possible
For the new line, Puratos and Uticon opted for a tower structure. Ingredients move by gravity to the mixer and then to the roller. No pumps were needed to transfer them. Space utilisation and process flow were therefore considered together.
This integrated perspective is also relevant to energy and food safety. Process choices determine the required temperatures and power ratings, while an early risk assessment clarifies the applicable hygiene requirements. Involving building designers, process engineers, logistics specialists and the quality department at an early stage makes it possible to factor in dependencies from the outset.
For food producers looking to grow on an existing site, this case offers practical pointers. An expansion needs to suit both the future factory and day-to-day operations during the works. The article shows how to bring these two perspectives together, and the role storage, routing, building layout and utilities play.
Want to find out more about this expansion? Visit the Haskoning website to discover how Puratos added capacity while production continued.
Een zakelijke vraag aan Haskoning (Consulting & Engineering Services)? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFood safety from design to audit
- SubjectSolutions
- CompanyHaskoning (Consulting & Engineering Services)