Baguettes that sell like hot cakes? That is only possible if you have complete control of the production process, in order to deliver the volume and the quality. It is a balance that Boulangerie de France wants to master even better by investing continuously in its production. In a recent project, new pipework was installed to maximise heat recovery. Stainless steel specialist Indinox delivered an impeccable result.

The Boulangerie de France factory only went live in 2016. At that time, one production line was running and the second was under construction. Diversi Foods's aim was to produce baguettes and speciality breads here. It was the start of a success story. In 2021, a new hall with an additional baguette line was already added. Why? "Because we produce the tastiest and best baguette," laughs Hannes Gabriel. As technical manager, he leads the automation team and is in close contact with the plant director on new investments. "I may be biased, but when I taste a baguette somewhere, I can immediately pick out ours. Mmmmm."

Quality

Achieving that taste calls for a strong focus on quality. Gabriel: "You do that by controlling your processes as well as possible, in order to absorb the variations inherent in working with natural products. In addition, we keep a very close watch on the products that roll off the line here. Whether they meet all the requirements we set ourselves for our products and the flavour profiles the customer wants." The range is varied, from baguettes with the finest crispy crust and the lightest crumb to the most original bread rolls. Besides its own brand, Diversi also produces under private label.

Onberispelijk leidingwerk voor stokbroodfabriek

Maximising heat recovery

Boulangerie de France employs around 90 people, spread over three shifts (Monday to Saturday). Together they produce about 10 tonnes of product per hour, which find their way across Europe. It is an impressive piece of teamwork, made possible only by automating the processes to a high degree. "A must here in Belgium because of the high labour costs, but also a must to guarantee quality. The fewer manual steps, the less chance of fluctuations," Gabriel knows. Boulangerie de France therefore keeps investing in its production equipment. In a recent project, for example, the piping network across the two halls was tackled. "We try to recover as much heat as possible in our processes and reuse it elsewhere in the factory. However, the mepla pipes that were installed turned out not to be reliable enough for the temperatures and pressures involved. By switching to stainless steel pipework, we could maximise heat recovery without the risk of weakening."

Hands-on approach convinces

This time, Boulangerie de France chose a stainless steel specialist: Indinox. "What immediately appealed to me was the technical, hands-on attitude of Stéphane (De Coninck, sales/project manager at Indinox). He didn't simply count the metres of pipe to draw up his quotation, but asked questions about how they could get the material in and where the constraints in the spaces were. That immediately gave us confidence that our project had been carefully thought through in advance, so that the actual work would run smoothly and efficiently. This is certainly not the biggest project: in total it involved about 900 m of pipe in 304 stainless steel. The challenge lay mainly in the logistics and in bringing everything to a successful conclusion with as little impact as possible on ongoing production," says Gabriel.

Onberispelijk leidingwerk voor stokbroodfabriek

Pragmatic

That pragmatism, which is ingrained in Indinox's DNA, also proved invaluable during the works, led by project manager David Rodriquez. "They were responsible for dismantling the existing network and installing the new one, including valves and insulation. There was no set of isometrics to serve as a basis. The Indinox team measured everything on site, then fabricated and installed it. They stayed on the ball with regard to our production, communicated well when problems arose and switched quickly when adjustments were needed. As a result, they stayed perfectly on schedule during those six weeks and delivered excellent results. That was proven by the pressure tests, which revealed no leaks, and by the fact that we have been able to recover heat to the maximum since April. A particularly positive first experience with Indinox, then." Something tells us it will not be the last.

A business enquiry for Indinox? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeBuilding and upgrading food factories
  • SubjectSolutions
  • CompanyIndinox
Share this article

Follow on FoodTec

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.