A pancake factory with a compelling story

Text Elise NoyezImage Beeuwsaert Construct

De nieuwe vestiging van Lipcas omvat productiefaciliteiten, een koel- en diepvrieszone, kantoren, een magazijn voor primaire grondstoffen en drie laadkades.
De nieuwe vestiging van Lipcas omvat productiefaciliteiten, een koel- en diepvrieszone, kantoren, een magazijn voor primaire grondstoffen en drie laadkades.

After a fire destroyed Lipcas’s production department in June 2022, the pancake and poffertjes producer wanted to get back up and running as quickly as possible. The company soon found a new site on a new industrial estate in Zwevezele through the West Flanders Intermunicipal Association. Working with architects JN architecten, construction coordinator Ann Stragier and main contractor Beeuwsaert Construct, it ultimately built a new, fully FAVV-compliant production facility in just six months.

Lipcas began as a local dairy business more than 60 years ago and has grown into a leading producer of pancakes and poffertjes. In Zwevezele, West Flanders, the family business produces between 20,000 and 30,000 kg of sweet batter products every day, which are then distributed to supermarkets in Europe, Canada, the United States and Indonesia. To minimise disruption to supplies for these customers after the fire in June 2022, Lipcas approached Beeuwsaert Construct at the end of 2022 to build a new production facility. “Despite the tight schedule, Beeuwsaert Construct was immediately willing to fit our project into its programme at short notice,” says COO Ruben Casteleyn. “That was obviously a big plus. Foundation work began in January 2023.”

Only along the Wingenesteenweg, by the offices, is the solid concrete volume interrupted by a projecting façade of glass and black joinery.

Precast concrete construction

Lipcas’s new site is just 500 m from the original production department and covers a total area of around 4,140 m². In addition to the production facilities, the building includes a chilled and frozen storage area, offices, a warehouse for primary raw materials and three loading bays. The project also included 2,870 m² of external works. “The building’s basic layout is relatively standard,” says Jo Martens, project manager at Beeuwsaert Construct. “All dimensions are designed for prefabricated construction, and the four façades are made from precast concrete panels. Only along the Wingenesteenweg, by the offices, is the solid concrete volume interrupted by a projecting façade of glass and black joinery. For fire safety, the building’s structure was also built in concrete. There was one exception: the roof over the production department. We had to allow for spans of up to 24 m, as well as enough space for cooling and ventilation systems, among other things. As a result, we used steel lattice girders instead of concrete beams.”

High standard of finish

The need for numerous technical installations, all of which had to be concealed above a suspended ceiling, is just one of the complexities involved in a food industry project. “The standard of finish on projects like this is considerably higher than in other industries,” says Martens. “As well as all the production facilities and systems, numerous stainless steel drainage channels had to be incorporated into the floor, and the finish included sandwich panels and epoxy flooring. This complexity is precisely what makes it so exceptional that we completed a fully FAVV-compliant production facility in around six months.”

To ensure efficient execution, delivery and installation times for materials were factored into the design phase from the outset.
The project required a high standard of finish, along with numerous technical installations and facilities.

Strong coordination

Martens attributes the short lead time above all to strong coordination. “Prefabrication obviously saves time, but it is the close coordination between the different teams and parties that really makes the difference. Together with the external construction coordinator, we managed this effectively in both the design and execution phases.” Casteleyn recalls the extensive discussions, including those about the choice of materials. “During the design phase, we gave a lot of thought to construction efficiency. Which materials could be delivered and installed quickly, and what would they cost? Beeuwsaert’s knowledge and insight played an important role in this. On site, the contractor then did everything possible to ensure the right team was in the right place at all times.” Martens explains: “We worked in several phases. First, the production hall was built, followed by the warehouse and the chilled and frozen storage area, and then the logistics section. However, our subcontractors did not wait until the shell was fully complete before starting work. By the time we finished the final shell phase, for example, the production department was already fully fitted out. This meant Lipcas could start baking pancakes and carry out trial runs in August 2023, in line with the planned schedule.”    

Have a business enquiry for Beeuwsaert Construct? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectNews
  • CompanyBeeuwsaert Construct
Share this article

Follow on FoodTec

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.